Consultancy Service for feasibility and design of ROB at Railway Phatak near Village Dantli, Jaipur.

Funding Agency: Government of Rajasthan

Location: Rajasthan

ROB at Railway Phatak near Village Dantli, Goner road, Jaipur The ROB is in Dantli village crossing on Jaipur-Sawai Madhopur railway line and cross the National Highway 11 connecting NH-12 near Goner village. 8 laning project under the jurisdiction of JDA connects main Jaipur city. The frequency of railway movement is very high (nearly 50 trains a day). This results is frequent closure of level crossing at this point and has therefore necessitated construction of ROB connecting NH-12 to NH-11 within the JDA limits 4 laning to 8 laning.

Actual Services provided by the Firm

• Conducting the topographical survey, L-section, Cross section by using Total Station. • Conducting the traffic survey for the replacement of level crossing with ROB. • Projecting the future traffic. • Preliminary design of ROB which consist of 2 central span of 21.5m on the railway boundary and 10 span of 17.30m on the prestressed concrete superstructure and on pile foundation. • Total length of the flyover is 700m which includes the RE walls. • It was principally accepted by the JDA and is being submitted to the Railway for the formal approval as per railway norms. The cost of the project is Rs. 20 crores for 4 laning the remaining 4 laning would be constructed in second stage and cost will be determined accordingly.